• 论文 •    

不确定环境下模具制造项目群随机调度

张沙清,陈新度,陈庆新,陈新   

  1. 广东工业大学 机电工程学院,广东广州510090
  • 出版日期:2009-07-15 发布日期:2009-07-25

Stochastic scheduling for multiple mould and die manufacturing projects under uncertainty

ZHANG Sha-qing,CHEN Xin-du,CHEN Qing-xin,CHEN Xin   

  1. School of Mechatronics Engineering, Guangdong University of Technology, Guangzhou 510090, China
  • Online:2009-07-15 Published:2009-07-25

摘要: 为确保模具按时交货,通过分析模具制造项目工期、费用与报酬的不确定性,以及项目返修频繁的特点,建立了基于离散时间马尔可夫链的模具制造项目群随机演化模型,并提出了求解该随机动态规划模型的算法框架。通过启发式策略仿真和Q学习,有效解决了“维数灾难”问题。最后结合示例阐述了该算法的执行过程,及其可行性与可靠性。

关键词: 模具制造, 随机动态规划, 马尔可夫链, 启发式策略, 仿真, Q学习

Abstract: To assure on-time delivery of mould and die, by analyzing uncertainties of the durations, costs and rewards as well as the characteristics of frequent repairing in the mould and die manufacturing project, a stochastic evolution model of multiple mould and die manufacturing projects was proposed based on a discrete time Markov chain. And an algorithm framework to solve this stochastic dynamic programming model was proposed. Through simulation of heuristic policies and Q-learning, the'curse of dimensionality'was overcome. Finally, the algorithm framework was explained by an example, and its feasibility and reliability were also verified.

Key words: mould and die manufacturing, stochastic dynamic programming, Markov chains, heuristic policies, simulation, Q-learning

中图分类号: